06/02/21
|
#59
|
DEPARTMENT OF MILITARY AFFAIRS
|
Authorize to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, to provide Construction of Baffled Range Closure Plate located at Center Strafford Training Site, in the amount |
$486,850 |
approved
|
|
01/22/21
|
#42
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for culvert rehabilitation and replacement in Stoddard under NH Route 9, on the basis |
$559,018 |
approved
|
|
01/22/21
|
#43
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for culvert rehabilitation in Bedford under NH 101 and Boynton Street, on the basis o |
$1.1M |
approved
|
|
09/23/20
|
#91
|
DEPARTMENT OF ADMINISTRATIVE S
|
Authorize the Division of Public Works Design and Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for the Center Strafford Water Upgrades and Site Improvemen |
$4.2M |
approved
|
|
01/22/20
|
#36
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for sidewalk curb ramp upgrades, on the basis of a low bid of $747,055. (2)Further au |
$747,055 |
approved
|
|
01/23/19
|
#44
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for replacing a structurally deficient hybrid culver that carries Batchelder Brook un |
$358,449 |
approved
|
|
07/27/18
|
#55
|
DEPARTMENT OF ADMINISTRATIVE S
|
Authorize the Division of Public Works Design and Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for an upgrade of the NH National Guard’s Rochester Motorpo |
$595,343 |
approved
|
|
06/20/18
|
#149
|
DEPARTMENT OF ADMINISTRATIVE S
|
Authorize the Division of Public Works Design and Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for the Waterline and Sprinkler Improvements at the Lakes R |
$511,473 |
approved
|
|
01/18/17
|
#20
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for reconstructing the at-grade railway-highway crossings, approaches and protective |
$318,573 |
approved
|
|
03/28/12
|
#135
|
DEPARTMENT OF TRANSPORTATION
|
Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for replacement of 1.3 miles of median box beam guardrail with median barrier located |
$1.6M |
approved
|